Viranşehir Solar Power Plant
The Solar Power Plant (SPP) investment, planned to have an installed capacity of approximately 12 MW, is planned to be established in Viranşehir, Şanlıurfa. The preliminary land allocation has been made, and an application for the SPP installation was submitted on October 31, 2023. A call letter was received on May 27, 2024, for the 3.75 MW portion of the project, and an additional 8.25 MW capacity was allocated on June 10, 2024. Thus, a total capacity of 12 MW has been allocated.
The EIA process commenced on 25 November 2024, and an EIA was obtained on 29 May 2025 for the 8.25 MW portion of the project. The EIA process for the 3.75 MW portion is ongoing.